After years of delay, work on San Francisco Plaza is finally underway; Contractor has 10 months to finish

Aug 15, 2017 | 0 comments

“Thank God, they’ve finally started.”

San Francisco Plaza workers remove old paving stones.

Rosa Chuchuca’s sentiment was shared Tuesday morning with two other women who sold clothing and household goods at San Francisco Plaza and who were relocated three weeks ago to Calle Padre Aguirre. The three stood at the northeast corner of the plaza, watching workmen stack old paving stones.

“We have to see it with our own eyes to believe it since nobody ever told us anything,” Chuchuca said, describing the frustration that many plaza merchants have felt as construction delays, first over design issues and most recently over a contract dispute, pushed back the project start date.”

Most of the debris has been cleared from the Plaza.

“At least now we have some idea of when we’ll be able to move back. They say it will be in a year but I think it will be a little longer,” she added.

Work on the rehabilitation of the plaza began in earnest Friday, after the new construction contract was finally signed.

According to Pablo Barzallo, director of the Cuenca Historical and Patrimonial Areas Commission, it isn’t just the merchants who are relieved. “The problems have put a strain on all of us, not just the people who work here but the people in the government who had hoped the project would have been completed by now.”

Barzallo feels confident that the project will be completed within the 10 months stipulated in the contract. “We are in the process of breaking the schedule into parts so we can provide better information to the merchants as well as to the transportation office, since they are rerouting traffic.”

President of the San Francisco Plaza Merchants Association says he is also feeling “more relaxed” seeing the project underway. “We’re still waiting for schedule details from the municipality but they have been more responsive lately, since the contract problems have been settled.”

CuencaHighLife

Dani News

Google ad

Hogar Esperanza News

Fund Grace News

The Cuenca Dispatch

Week of April 28

General Motors Auto Parts Manufacturer Laments: “Today Marks a Dark Day for the National Industry”.

Read more

Minister Requests Resignations in Termogás Machala, Dubbed ‘Epicenter of Energy Inefficiency’.

Read more

Chevrolet to Cease Car Assembly in Ecuador by August, Production to Halt in Colombia.

Read more

Google ad

Discounts at Gran Colombia News

Country Ranch Living News

Country living News