Tram will require nine months of training and testing before it goes operational

Oct 4, 2017 | 0 comments

Cuenca’s transportation director says the city’s tranvia system will require nine months to train personnel and to test tramway and computer systems before it offers service to the public. According to Jaime Guzmán, most of the preparation work will be conducted as project construction is completed.

Tram cars in the rail yard on Av Unidad Nacional.

Guzmán said the city hopes to name a tram operations company by the end of the month to conduct the prep work. Two companies, one from Medellin, Colomibia and the other from the Spanish Canary Islands, are negotiating with the city for the project.

“The preparation work is an essential part of a successful operation,” Guzmán says. “Tram operators must be trained to international professional standards. We must also ensure the physical integrity of the system, which includes the rolling stock, track and switches, and make sure the computer system is fully functional.”

Guzmán says that 40 conductors will be trained during the preparation phase.

Mayor Marcelo Cabrera reported Monday that a technical committee has completed its review of the project management contract to be signed next week with the French consortium ACTN.

CuencaHighLife

Dani News

Google ad

Hogar Esperanza News

The Cuenca Dispatch

Week of April 28

General Motors Auto Parts Manufacturer Laments: “Today Marks a Dark Day for the National Industry”.

Read more

Minister Requests Resignations in Termogás Machala, Dubbed ‘Epicenter of Energy Inefficiency’.

Read more

Chevrolet to Cease Car Assembly in Ecuador by August, Production to Halt in Colombia.

Read more

Country living News

Discounts at Gran Colombia News

Fund Grace News

Country Ranch Living News

Google ad