Blackouts are ordered in at least four provinces as hydroelectric plants fail to meet demand
The National Electricity Operator (Cenace) ordered emergency blackouts in several provinces Monday night as low water conditions reduced power generation at the country’s major hydroelectric plants.

Designed to supply 1,500 megawatts of electricity, the Coca Codo Sinclair plant in Napa Province rarely produces more than 1,200 mw due to siltation and mechanical problems.
Cenace ordered the disconnections at 3:30 p.m. when it said it would not be able to meet the demand of 5,400 megawatts early Monday night. According to a Cenace spokesman, the blackouts saved 620 megawatts.
Blackouts were reported in Pichincha, Tungurahua, Cotopaxi and Pastaza Provinces. According to a Quito radio station, as many as 200,000 households were without electricity in the Quito suburbs of Tumbaco and the Valle de los Chillos.
The Cenace spokesman believed that power would be restored to affected areas by about 10 p.m. as demand decreases. He added that blackouts could be repeated and possibly extended Tuesday if rain does not raise water levels at the power plants.
The spokesman said that “drastic collapse” of water flow at the Coca Codo Sinclair hydro plant in Napa Province and the three plants at the Paute-Mazar complex in Azuay Province were the reason for the blackouts. In addition, the Minas San Francisco plant, also in Azuay, was operating at a minimum level due to the low flow rate of the Rio Jubones.